John165
Member
- Location
- New Mexico
- Occupation
- Journeyman
We are inspecting a job, where the notes say #6 wire but the panel sch says # 10. Which would you go by? The contractor went by the panel sch. I know that the contractor should have clarified with engineer / arch. which they didn't. Thanks John