Have a duct bank between existing service to remain feeding a building be demolished and they want the duct bank demo'ed and the circuits will no longer be used. Would you as the electrical contract HAVE to remove the conductors or couls you disconnect and safe off with removal by others? Don't think others removing them would make any sense? Could the conductors be abandoned somehow? What would be most practical? Thanks.