Providing my own contract

Moore Power

Member
Location
Washington
Occupation
Electrical Contractor
Thanks in advance. I've been in business 3.5 years doing mostly commercial T.I.s with nation wide contractors. Now with 3 employees I am trying to get bigger projects that I can keep a couple guys on for a while. My issue is funding, generally the project is close to completion before I get my first check with the "pay when paid" terms of the contract the GC supplies. Do you guys invoice mobilization? How do I take that next step without taking out a loan? I'm assuming on larger projects ECs are providing their own contracts with their own terms. Any advice, contract template, experience is greatly appreciated. I jumped in blind and have been learning along the way.
 
It is fair to have a mobilization line item on your schedule of values, but it’s not typical to provide your own contract to a GC.

The terms can always be negotiated though. If you plan to take on a job you can’t float you need to discuss that with the GC before signing. Pay when paid is not legally enforceable in some states. But the GC may pass on you to work with a contractor that has the financial means to wait.

I would try to negotiate the minimum payment you can accept and survive until the owner pays a draw to the GC.

You may also try to negotiate having no retainage held on stored materials. The GC is often working under the terms of the owners financing and will have to come out of pocket to cover you.


Sent from my iPhone using Tapatalk
 
It is fair to have a mobilization line item on your schedule of values, but it’s not typical to provide your own contract to a GC.

The terms can always be negotiated though. If you plan to take on a job you can’t float you need to discuss that with the GC before signing. Pay when paid is not legally enforceable in some states. But the GC may pass on you to work with a contractor that has the financial means to wait.

I would try to negotiate the minimum payment you can accept and survive until the owner pays a draw to the GC.

You may also try to negotiate having no retainage held on stored materials. The GC is often working under the terms of the owners financing and will have to come out of pocket to cover you.


Sent from my iPhone using Tapatalk
Thank you. That is very helpful.
"I would try to negotiate the minimum payment you can accept and survive until the owner pays a draw to the GC. "
Are you saying that this payment would be due after signing the contract? Is 10% mobilization on an $80,000 job reasonable? Either way the key seems to be developing a relationship with a local GC that wants us on the job. Thanks again.
 
Top