Hello, I’m gonna be doing an electrical duct bank with no wire involved. Material all included. 10-4” sch40 10’ sections 100’ length. Depth of trench
4’ 8” soil type (sand) just the earth work , compaction,and conduit install with spacers every 5’ no concrete in casement. Looking for some opinions on quoting this. Thank you