- Location
- WI & AZ
- Occupation
- Electrician
I have a duplex and each side has a 100A service. I'm replacing the overhead service. The way I interpret the code, the line side of the service entering the 2 position meter pack would have to be sized at the full 200 amp ampacity and the two sets of load side service entrance conductors in individual conduits would fall under the 83% reduction. Correct?