0-10v dimming 1 switch, 2 breakers

Status
Not open for further replies.

Fulthrotl

~Autocorrect is My Worst Enema.~
One switch controls the Dayligting with a photocell.
The other switch controls lights outside the daylight zone.
As long as the power pack is powered from the geny then things should be ok. right?

Heck it's T-bar , if the owners agent screwed up then it's a change order. That was the deal in writing.

occupancy sensors? astronomical time clock?
is the photocell and related controls listed as compliant for this work?

does the approved drawings have a block control diagram for the lighting control?
are the lighting control devices specified on the drawings?

as long as the controls are powered from the backup power source, they will continue
to operate the lights.

will things be ok? not based on the information you've provided so far.
not enough information to determine if it's compliant.

put it in and see how it flies? go for it. i've currently got five jobs circling
the drain, that i can't certify, that sound a lot like this one sounds.

one of them's been there since feb. GC isn't responding to either email or
phone calls. GC has not paid his bill for certification, either. GC is about to
have job failed this week, which is sorta like the car you are trying to sell
being listed as a gross polluter.

GC hasn't paid electrical contractor, either. good luck with your project.
 
occupancy sensors? astronomical time clock?
is the photocell and related controls listed as compliant for this work?

does the approved drawings have a block control diagram for the lighting control?
are the lighting control devices specified on the drawings?

as long as the controls are powered from the backup power source, they will continue
to operate the lights.

will things be ok? not based on the information you've provided so far.
not enough information to determine if it's compliant.

put it in and see how it flies? go for it. i've currently got five jobs circling
the drain, that i can't certify, that sound a lot like this one sounds.

one of them's been there since feb. GC isn't responding to either email or
phone calls. GC has not paid his bill for certification, either. GC is about to
have job failed this week, which is sorta like the car you are trying to sell
being listed as a gross polluter.

GC hasn't paid electrical contractor, either. good luck with your project.

All the components are T-24 compliant to best of my knowledge.
Daylight sensor , dimmers, Astro- time clock.
If not again not our problem. The GC and the owner took that out of our hands.
Once again they only thing we are concerned as we do not want to fry any components when connecting different lights from different power sources to the same 0-10 volt wire. It appears from you nice folks that this will not be the issue. We were not allowed involvement in the process of the lighting.
We are covered with language that if installed as per plan and does not work any change will be a extra paid at xxx dollars per man hour. We placed this caveat because of what we read here at MH.

So our fingers crossed.

Thanks for all the help.
 