Re: 200 amp service changeout estimating
You only have about $400.00 in material. Even if you pay your best mechanics $500.00 each that leaves a $2000.00 profit. If the market will bear it - God bless you. I don't know about anyone else but I'm moving to Boston next week !!!200A Changeover I figure 2 men one day. We do from the point of attachment down, We supply weatherhead,PVC,meter socket,main breaker panel and all breakers and connectors. Also the 2/O copper.And the 4 copper
$3400 typically, subject to adjustment