james cohee
Member
thanks for all the input fellas. designing for voltage drop is primary concern as a pv install is planned in the future. as they are only 20% efficient at best every watt counts. i would love to use transformers to make the job easier but my understanding is that they use 300-400 watts 24-7 365. the thought of having pv to power transformers is not so appealing. so it appears we will be stuck wrestling with this monster wire. the reason we problobly will not go with al is bcause it is near the coast and the salt air is harsh on the al. it is a fairly straight run but it appears i will need to hire out the actual pull to someone with a pullin rig. ??? with efficiency in mind, should i go from property line meter to garage panel, from garage panel to house. or from property line meter to house with a loop by the planned garage that we could tap into later when garage is built. generator will be by garage panel. ps 400 amp service is not an option w/o a lengthy fight.