From a Plan Reviewers stand point a building would include all portions of the building from the roof of the structure to the footing of the structure.Not always though, think crawl space under a dwelling. Conduit could lay on the ground.
From a Plan Reviewers stand point a building would include all portions of the building from the roof of the structure to the footing of the structure.Not always though, think crawl space under a dwelling. Conduit could lay on the ground.
And from the NEC stand point 230.6 specifically spells out what is considered outside.From a Plan Reviewers stand point a building would include all portions of the building from the roof of the structure to the footing of the structure.
if concrete gets poured and it is at least two inches below surface of concrete it is legal... , I could be wrong...lol.
From a Plan Reviewers stand point a building would include all portions of the building from the roof of the structure to the footing of the structure.
So what do you think he meant when he said this?
[/COLOR]Roger
I know what he meant, and have tried to argue it in Jamaica... was still made to put the trench in and call the inspectors back out later... because the concrete was not done...
Inspector stated that too many do not do the concrete work after approvals given so they insist on full trench now, unless concrete work done.
If the project is not complete a final or CO will not be issued, this includes concrete.I know what he meant, and have tried to argue it in Jamaica... was still made to put the trench in and call the inspectors back out later... because the concrete was not done...
Inspector stated that too many do not do the concrete work after approvals given so they insist on full trench now, unless concrete work done.
You do realize that in many other applications the pipe still has to be buried despite 4” of concrete going over it.
I don't know what you are trying to say here but, if my installation is compliant with the NEC and there are no formal amendments then the NEC is the end of the story, if your inspectors are allowed to make up their own rules then you and others should try to change that.but the depth of burial required changes by the fact you are placing it under concrete and some pipe can be buried in concrete as long as it is far enough inside the concrete... as long as it is direct burial rated... may not be up to date on all the US codes but know that you can put cable in conduits in concrete
but the depth of burial required changes by the fact you are placing it under concrete and some pipe can be buried in concrete as long as it is far enough inside the concrete... as long as it is direct burial rated... may not be up to date on all the US codes but know that you can put cable in conduits in concrete
250.6.. doesnt that have to do with grounding and neutral paths? Will try to find it but I thought 250 was grounding...
Conductors that are considered as being outside a building (230.6):
- Beneath a building under not less than 2 in. of concrete or
- Beneath a building where installed in conduit and under not less than 18 in. of earth
- Within a building in a raceway encased in concrete or brick not less than 2 in. thick
So, if it is a conduit at least two inches under concrete at least two inches thick, it is covered? Or have I misread this> >
View attachment 21109 of course, this one calls for 24 inches... if I read it right...
In what scenario?
JAP>
Conductors that are considered as being outside a building (230.6):
- Beneath a building under not less than 2 in. of concrete or
- Beneath a building where installed in conduit and under not less than 18 in. of earth
- Within a building in a raceway encased in concrete or brick not less than 2 in. thick
So, if it is a conduit at least two inches under concrete at least two inches thick, it is covered? Or have I misread this> >
Even though the OP didn't answer my question in post # 15, from his original discription it appears as though he is describing service entrance conductors and not a feeder so 230.6 (1) is correct.
Roger