Does 2017 210.63 receptacle requirement apply to mechanical rooms separate floors in multi story bldg?
There are several different requirements in 210.63. Do these mechanical rooms have HACR equipment?Does 2017 210.63 receptacle requirement apply to mechanical rooms separate floors in multi story bldg?
I just assumed they did.There are several different requirements in 210.63. Do these mechanical rooms have HACR equipment?
I still say yesThese rooms provide the hvac for the hallways, etc.