Subsection 250.30(A)(1)(3)(c) in the 2020 NEC pertains to Delta-Connected Systems, in particular 3-phase, 3-wire delta systems with a grounded conductor. Is this the same thing as a Corner Grounded system? Thanks in advance.
 
I only had two 480V corner grounded deltas and the POCO wanted us to replace them, which we did. I belive a they are the same.
(Note correct terminology is section...most use article for a section citation, which is me is like saying 110 and 220 V. Its ok...kindof)
 
Subsection 250.30(A)(1)(3)(c) in the 2020 NEC pertains to Delta-Connected Systems, in particular 3-phase, 3-wire delta systems with a grounded conductor. Is this the same thing as a Corner Grounded system? Thanks in advance.
Yes, that sub-section is talking about a 3 wire, corner grounded, delta system.
 
Thanks for clarifying. One other thing I'd like to clarify is proper terminology: Is 250.30(A)(1)(3)(c) considered a sub-section or section as tom baker is suggesting? I though 250 was the article 250.30 was the section and anything further designated with parenthesis under 250.30 was considered a subsection. Am I missing something?
 
My use of section is from Mike Holts understanding the NEC and the dozen or so of his seminars I have attended, never heard him say subsection. There is an NFPA style manual if you want to track it down.
 
Thanks for clarifying. One other thing I'd like to clarify is proper terminology: Is 250.30(A)(1)(3)(c) considered a sub-section or section as tom baker is suggesting? I though 250 was the article 250.30 was the section and anything further designated with parenthesis under 250.30 was considered a subsection. Am I missing something?
250 is an Article
250 Part I is a part (note that this can become important as parts can act as scopes for the material that follows...for example a part for over 1000 volts...that material in that part only applies to equipment operating over 1000 volts)
250.30 is a section
250.30(A) is a first level subdivision
250.30(A)(3) is a second level subdivision
250.30(A)(3)(c) is a third level subdivision
 