hhsting
Senior Member
- Location
- Glen bunie, md, us
- Occupation
- Junior plan reviewer
I have building that already has 1200A 277/480V three phase main service switchboard, 1200A 277/480V electric utility into the switchboard.
The switchboard has 100A spare breaker and overall load should be fine if we added new loads. However, the owner wants in same building 208V/120V, three phase 200A new electric utility service. We said he can get thru 100A switchboard spare breaker feeding transformer 480V to 208/120V three phase but wants additional utility service.
Not sure if the above would fall under 230.2(D) or not. Can the code allow this additional utility service 200A 208V/120V three phase or we have to go from 100A switchboard breaker to transformer 480V to 208/120V three phase?
The switchboard has 100A spare breaker and overall load should be fine if we added new loads. However, the owner wants in same building 208V/120V, three phase 200A new electric utility service. We said he can get thru 100A switchboard spare breaker feeding transformer 480V to 208/120V three phase but wants additional utility service.
Not sure if the above would fall under 230.2(D) or not. Can the code allow this additional utility service 200A 208V/120V three phase or we have to go from 100A switchboard breaker to transformer 480V to 208/120V three phase?
Last edited: