I am working on a job with a 225kVA transformer 277/480 primary, 120/208 3 phase secondary. There are 2 sets of 4#500, 1/0G in 4"C going to an existing 800 MCB panel, "DPL2" which is 10' away from the transformer.
I am putting a 225A panel and tapping off this panel, "DPL2", and putting on new equipment for the restraunt remodel.
I got a comment from the city that the secondary feeder from the transformer is "violating the TAP fules. Please upsize or reduce OCP in DPL2." I was looking at 240.3.B and 240.21.C for reference.
Any ideas on how I can respond. Or what would be the best design to correct the issue?