jucesanc
Member
- Location
- California, Bay Area
I'm creating an installation plan for heat tracing, and am having trouble understanding how to power it.
The manufacturer recommends a 2-pole GFCI circuit breaker. The heat tracing cable is rated for 100-130 Vac. The cable is 3W/ft and will be about 250 ft long.
Is it possible to provide 120V with a 2-pole breaker and how would I wire that up?
We have spares on a 208/120V 3phase, 4 wire panel.
The manufacturer recommends a 2-pole GFCI circuit breaker. The heat tracing cable is rated for 100-130 Vac. The cable is 3W/ft and will be about 250 ft long.
Is it possible to provide 120V with a 2-pole breaker and how would I wire that up?
We have spares on a 208/120V 3phase, 4 wire panel.