oneelectron
Member
I have used this wire method for years, passing with flying colors. Lately I have been working for a company that says this is a violation. Have I been miss led before by code enforcement or this new shop, NEC seems hazy in this area.
Using 12-3 on a 2 pole 20, I pull to a bedroom for rec. pigging the neutral I pull the second circuit to the GFCI rec in a bath.
Where is there a violation and why?
Using 12-3 on a 2 pole 20, I pull to a bedroom for rec. pigging the neutral I pull the second circuit to the GFCI rec in a bath.
Where is there a violation and why?