hhsting
Senior Member
- Location
- Glen bunie, md, us
- Occupation
- Junior plan reviewer
I have 4 pole ATS. Normal side is fed by main service disconnect and emergency side is fed by generator 208/120V three phase has neutral going to the ATS. Same on normal side. The building has non balance loads so neutral is fed downstream from ATS.
Plans call for the generator to be Non separately derived. I am just confused.
Can one have 4 pole ATS and generator be Not separately derived?
Plans call for the generator to be Non separately derived. I am just confused.
Can one have 4 pole ATS and generator be Not separately derived?