A/A Fuel GTX
Senior Member
- Location
- WI & AZ
- Occupation
- Electrician
I think I'm right on this but want to throw it out for opinions before I begin the job. I'm installing a 400A service for a farm. There will be a 400A ( 320A continuous ) meter socket fed from the POCO's lateral feeding a 400A MLO load center. From the load center, I will run three feeders to three separate buildings with the OCPD for each building in the load center. Of course, each building will have a disconnect of its own. The meter/load center combo will be in the middle of the property mounted on a board with 6 X 6 posts for support. In this scenario, I don't think I need a main breaker for the 400A load center since I'm below the 6 OCPD requirement..........Correct?