For a chiller replacement project, we are removing 4,160V chillers and replacing them with 480V chillers. (the new chillers are smaller making 480V a better choice)
I will be specing around a Square-D Model III unit substation. This contains the 1,000KVA transformer and switchboard in one package.
The unit substation will be 40 feet and out of site from the 4,160V switchgear section that will feed it.
The 4,160V switchgear is fused and has a disconnect.
My question is, does the unit substation require a main disconnect ahead of the transformer within the substation itself?
Thanks
I will be specing around a Square-D Model III unit substation. This contains the 1,000KVA transformer and switchboard in one package.
The unit substation will be 40 feet and out of site from the 4,160V switchgear section that will feed it.
The 4,160V switchgear is fused and has a disconnect.
My question is, does the unit substation require a main disconnect ahead of the transformer within the substation itself?
Thanks