sparkyguy545
Member
Restrictions in 450.21 (and all examples I can find) list various construction limitations focused on installations which exceed 112.5 kVA. What if I have 2 x 75 kVA xfmrs in the same room? Since each transformer is below the 112.5 kva limit, do the construction requirements for smaller transformers apply; or because the aggregate is 150 kVA (which is above the 112.5 kVA limit) am I required to follow requirements for the larger transformers?