PCN
Senior Member
- Location
- New England
We have a 500 kva padmount transformer feeding a new building. The secondaries to the main building consist of 4 sets of 500's, that go through CT's in the transformer vault which is provided by the POCO.
Now they want to add an out building that will be powered from that same xfmr.....but metered seperatly. My question is, when we add that 5th set of feeders for the out building, can they be routed around the CT's in the vault to allow seperate metering say in a CT can on the out building?
Seems like a no brainer to me, but my boss (the P.E.)thinks this will not work.
I have not asked the POCO this question yet.
Now they want to add an out building that will be powered from that same xfmr.....but metered seperatly. My question is, when we add that 5th set of feeders for the out building, can they be routed around the CT's in the vault to allow seperate metering say in a CT can on the out building?
Seems like a no brainer to me, but my boss (the P.E.)thinks this will not work.
I have not asked the POCO this question yet.