kenaslan
Senior Member
- Location
- Billings MT
Only one jurisdiction has required an emergency generator for all the Dialysis clinics I have designed. However I think that 517.33(A)(8)e calls out the requirement for receptacles in a dialysis room to be on a "Critical Branch". As defined by 517.2 a Critical branch is connected to alternate power source. The owner of these nation wide facilities has directed me to only engineer a power generator when told to by the AHJ.
So the question is, Is an emergengy generator required or not. Like I said, after over 100 installations only one has required the installation of an emergengy power generator.
Ken
god I love this forum
So the question is, Is an emergengy generator required or not. Like I said, after over 100 installations only one has required the installation of an emergengy power generator.
Ken