I am on a new construction project for which we have several 5kV motors that have been sitting On-Site waiting to be installed and operated. The motors have been sitting for some time now, and most of the time have not been stored very well.
I have been telling the contractor for some time now that because these motors have been sitting around not running, we need to periodaclly turn the shafts, as well as hook up the heaters inside the motors. The contractor has been arguing with me that this is not necessary.
What are some reasons I can back my argument with, as to why we need to to routinely spin the shafts and put the heaters on the motors?
I have been telling the contractor for some time now that because these motors have been sitting around not running, we need to periodaclly turn the shafts, as well as hook up the heaters inside the motors. The contractor has been arguing with me that this is not necessary.
What are some reasons I can back my argument with, as to why we need to to routinely spin the shafts and put the heaters on the motors?