First time here with an important question I hope can be answered. Ive done a search and read all the posts but couldn't find the answer i'm looking for.
I have a 200A - 240v Delta 3 phase service that has just been installed. I'm having a 75kva transformer hooked up right after the 200A fused disconnect. The disconnect is hooked up directly back to back of the meter can. It is a 480v - 240v transformer which will be reversed fed.This service is dedicated soley for 1 machine running on 480v. I have 3 questions.
1) When reversing the transformer does the 240v line in go to the (x) and the 480v line out go to the (H) which in turn goes to the machine. And / or do you change the 3 wires on the coils currently going to (H) that are for different voltages.
2)NEC says ocd rated at not more than 125% which is 225A. So does that mean it can be less as in my 200A fuses?
3) How is this suppose to be grounded? Currently the ground from the disconnect goes to ground on copper strip to transformer case. With ground from machine going to this same location. And solid copper from this same location to metal beam of building.
The inspector came and looked at the meter can and fused disconnect and ok'd this but he wants the transformer and machine hooked up before he gives his final approval.
I have been getting multiple different answers with the questions above and the electrician is saying none of this is right and that the inspector will not pass it. I hope I can get the RIGHT answers here so that I may get this machine up and running as soon as possible.
If more info is needed let me know.
All help is greatly appreciated,
Doug
I have a 200A - 240v Delta 3 phase service that has just been installed. I'm having a 75kva transformer hooked up right after the 200A fused disconnect. The disconnect is hooked up directly back to back of the meter can. It is a 480v - 240v transformer which will be reversed fed.This service is dedicated soley for 1 machine running on 480v. I have 3 questions.
1) When reversing the transformer does the 240v line in go to the (x) and the 480v line out go to the (H) which in turn goes to the machine. And / or do you change the 3 wires on the coils currently going to (H) that are for different voltages.
2)NEC says ocd rated at not more than 125% which is 225A. So does that mean it can be less as in my 200A fuses?
3) How is this suppose to be grounded? Currently the ground from the disconnect goes to ground on copper strip to transformer case. With ground from machine going to this same location. And solid copper from this same location to metal beam of building.
The inspector came and looked at the meter can and fused disconnect and ok'd this but he wants the transformer and machine hooked up before he gives his final approval.
I have been getting multiple different answers with the questions above and the electrician is saying none of this is right and that the inspector will not pass it. I hope I can get the RIGHT answers here so that I may get this machine up and running as soon as possible.
If more info is needed let me know.
All help is greatly appreciated,
Doug
Last edited: