IslanderVT
Member
- Location
- Northern VT
- Occupation
- Engineer
Hi Folks,
I'm working on a job to install an EV charger in a residential garage. The loadcenter is original to the home, which was built in the mid 90's.
The service entry is buried 4/0 Al with a meter main and 200A breaker at the pole. Because of the length of the secondary's, the main panel is derated to 150A per utility requirement, and is located inside the residence. The loadcenter is in good shape and its in a clean area, so we would rather leave it as is.
The plan is to install a 48A Emporia charger to get full charging capacity of the EV. In order to achieve 48A, it needs to be hardwired, otherwise it derates to 40A if using a 14-50 socket. We plan to run 6/3 Romex through the basement, then a J-Box with polaris lugs, and a short run of exposed 6/3 MC in the garage to the charger on the wall.
The only label in the loadcenter says max capacity is 150A. No notes about busbar capacity. I would think its the same busbar as a 200A loadcenter, but it doesn't say so.
I understand EV chargers to be a continuous load. If we apply the 120% rule to the 150A loadcenter, it's only rated for adding a 30A continuous load, which is obviously a no-go for a 48A EV charging load.
My question is...does anyone know if these older T&B loadcenters use 200A (or better) busbars? If so, does anyone know of documentation on this?
We could swap the loadcenter to a new one with 225A busbars...which is probably wise...but that greatly increases the scope and cost of the job.
Thanks in advance for the insight!!
I'm working on a job to install an EV charger in a residential garage. The loadcenter is original to the home, which was built in the mid 90's.
The service entry is buried 4/0 Al with a meter main and 200A breaker at the pole. Because of the length of the secondary's, the main panel is derated to 150A per utility requirement, and is located inside the residence. The loadcenter is in good shape and its in a clean area, so we would rather leave it as is.
The plan is to install a 48A Emporia charger to get full charging capacity of the EV. In order to achieve 48A, it needs to be hardwired, otherwise it derates to 40A if using a 14-50 socket. We plan to run 6/3 Romex through the basement, then a J-Box with polaris lugs, and a short run of exposed 6/3 MC in the garage to the charger on the wall.
The only label in the loadcenter says max capacity is 150A. No notes about busbar capacity. I would think its the same busbar as a 200A loadcenter, but it doesn't say so.
I understand EV chargers to be a continuous load. If we apply the 120% rule to the 150A loadcenter, it's only rated for adding a 30A continuous load, which is obviously a no-go for a 48A EV charging load.
My question is...does anyone know if these older T&B loadcenters use 200A (or better) busbars? If so, does anyone know of documentation on this?
We could swap the loadcenter to a new one with 225A busbars...which is probably wise...but that greatly increases the scope and cost of the job.
Thanks in advance for the insight!!