1st photo - waste pipe (which probably pre-existed service equipment) is directly over service equipment. Other that potentila damage from leaks, are there any other concerns?
2nd photo - 4 story building + basement - looking for confirmation that non-metallic sheathed is OK up to 4 stories. There are also some wire support issues present.
3rd photo - Does anyone know why someone would provide a shroud, made out of ceiling tiles, over the tops of light fixtures?
4th photo - Is it correct to conclude that the National Electrical Code, Section 110.12(C), Integrity of Electrical Equipment and Connections does not apply here?
http://i15.photobucket.com/albums/a352/TonyPE/IMGP2344_edited-1.jpg
http://i15.photobucket.com/albums/a352/TonyPE/IMGP2345_edited-1.jpg
http://i15.photobucket.com/albums/a352/TonyPE/IMGP2405_edited-1.jpg
http://i15.photobucket.com/albums/a352/TonyPE/IMGP2406_edited-1.jpg
2nd photo - 4 story building + basement - looking for confirmation that non-metallic sheathed is OK up to 4 stories. There are also some wire support issues present.
3rd photo - Does anyone know why someone would provide a shroud, made out of ceiling tiles, over the tops of light fixtures?
4th photo - Is it correct to conclude that the National Electrical Code, Section 110.12(C), Integrity of Electrical Equipment and Connections does not apply here?
http://i15.photobucket.com/albums/a352/TonyPE/IMGP2344_edited-1.jpg
http://i15.photobucket.com/albums/a352/TonyPE/IMGP2345_edited-1.jpg
http://i15.photobucket.com/albums/a352/TonyPE/IMGP2405_edited-1.jpg
http://i15.photobucket.com/albums/a352/TonyPE/IMGP2406_edited-1.jpg