whisenhuntpowersolutions@
Member
- Location
- Houston
- Occupation
- Electrician - Generator Installer
I have an existing Service Entrance with an externally mounted 200A Main Disconnect adjacent to the Utility Meter. The Disconnect feeds through the wall into the Load Center. I plan to install a Non-Service Rated 200A Transfer Switch on the outside wall adjacent to the existing Main Disconnect. According to code, I should be able run both the cables from the load side of the Main Disconnect (since they are protected by the Main Disconnect CB) and the cables feeding the Load Center from the Transfer Switch in the same raceway since they are considered feeder cables and not service cables. However, is it ok for me to run the feeder cables through the Main Disconnect Enclosure into the nipple connecting the Main Disconnect to the Load Center? ```