Rudy2153
Member
- Location
- California
- Occupation
- Journeyman Residential Electrician and Project Engineer.
The company I work for was hired to swap out the Zinsco Sub panels in a 150 or so condos recently. The work is now complete and even though the panels have a bond wire from the uffer of the building, the sub feed does not have a ground in the cable set (1\3 SER aluminum). The existing uffer to each panel is a 10 gauge solid bare copper and the sub feeds are on 100 amp breakers. Should I have run a new #8 ground to the mains for each sub panel? The existing mains will be changed in the future.