We have 0.48 KV (Main -Tie-Main) switchgear (PCC-21-01)fed from 13.8 KV/0.48 KV transformer. It is a 4000A switchgear.
I am confused while understanding the Arc flash study report. Please help me in understanding the format and which label goes to where. Please see the attached.
How come CB in the switchgear has more Incident energy than the Switchgear? What does Danger mean in the Risk Category level?
I am confused while understanding the Arc flash study report. Please help me in understanding the format and which label goes to where. Please see the attached.