- Location
- Illinois
- Occupation
- retired electrician
Re: Back Breaking Pull?
Wes,
Don
Wes,
Using that logic, each length of conduit is a short section and you could lay the wire on the ground and slide the "short sections" of conduit over the wire.If that 8' section were removed and added after the main pull, it would indeed be a "short section".
That section applies to installations where the conductors are directly buried, not to conductors that are installed in a raceway system.Instead try 230.32
It most certainly does. It is no longer a short section of raceway used to protect the conductors, it is a raceway system and compliance with 300.18 is required.I do not believe that because you have elected to run conduit all the way between the two points this is altered.
Don