Is it required to bond a metal pull box when splicing sub feeders straight through pull box
3/0 AWG and above
3/0 AWG and above
The code reference is in post #2. Since you're splicing the circuit conductors you need to connect the EGC's to the box. Dumb but required. If there was no wire type EGC you wouldn't have to do anything.I can’t find the definition in the code that specifies that install. Does anybody have it ?