The Everlasting Know-it-all!
- Location
- Madison, WI, USA
- Occupation
- Master Electrician and General Contractor
Quick question. I'm installing a 100kva 480-208 transformer on a new 1200A 480v service to serve existing lighting and 120v receps. The primary overcurrent device will originate from the mdp and the secondary will connect to a 200A main breaker panel. Since it's a separately derived system, i know i need a GEC to the water main. My question is, does the GEC for the mdp and the GEC for the SDS need to be bonded at some point? Also, does the SDS need a supplemental grounding electrode such as ground rods?