kyleapec
Member
- Location
- siloam springs arkansas
I am working on a job where the submittals on multiple HVAC equipment is different than the HVAC equipment schedule. As an example on a VAV we have an MCA of 36.90A and an MOP of 40A, the breaker shown by the engineer on the panel schedules are 35A breakers. I am worried about nuisance tripping, my understanding is that it is not a code violation. Though I do think it is a suboptimal design. The mechanical engineer is saying it is fine and to proceed, should I drop it or am I correct in my worries, thanks.