What is wrong on following list (if anything)?
Property with two buildings (cemetery):
Pad Mount transformer (so far so good)
Meter on post next to transformer.
Service lateral (underground) from meter to Building A about 50 feet away (to panelboard with MCB) (I don't really have a question on Building A)
Disconnect next to meter connected to the same meter - non-fused serves Building B.
Underground service lateral (in conduit) to Building B about 150 feet away.
Conduit out of ground and up side of building to a box maybe 15 feet up.
Bare insulated conductors through a roof/attic space to just above the panelboard (maybe 30 feet).
Conduit from ceiling down to the panelboard which has a main circuit breaker.
Property with two buildings (cemetery):
Pad Mount transformer (so far so good)
Meter on post next to transformer.
Service lateral (underground) from meter to Building A about 50 feet away (to panelboard with MCB) (I don't really have a question on Building A)
Disconnect next to meter connected to the same meter - non-fused serves Building B.
Underground service lateral (in conduit) to Building B about 150 feet away.
Conduit out of ground and up side of building to a box maybe 15 feet up.
Bare insulated conductors through a roof/attic space to just above the panelboard (maybe 30 feet).
Conduit from ceiling down to the panelboard which has a main circuit breaker.