I have an 800 amp 120/208 3 phase busway in a welding shop. Feeds 11 welding booths.
They would like to take half the welding booths and move them to the other side of the shop.
I would like to tap the existing 800 amp feeders and feed the relocated 5 boths on the other side of the shop.
I do not see anything in the NEC that would not allow me to do this, am I missing somehting? Is this legal? 25'-0" max tap distance?
Thanks.
They would like to take half the welding booths and move them to the other side of the shop.
I would like to tap the existing 800 amp feeders and feed the relocated 5 boths on the other side of the shop.
I do not see anything in the NEC that would not allow me to do this, am I missing somehting? Is this legal? 25'-0" max tap distance?