highlakeselectric
Member
- Location
- bend or
Additional equipment is being installed in an existing industrial plant. Addition will require a new 480 volt sub distribution panel to feed these loads none of panels rated 100%
a) 480/277 lighting panel supplying 535 KW florescent lights
b) 2-250 hp 480 volt 3 phase air compressors
c) 480/208y/120 3 phase transformer which supplies
5- 10 hp 208 3 phase pump motors
3- 25 hp 208 3 phase vacuum pump motors
17- 20 amp 120 volt punch press receptacles
8-30 amp 120 volt volt drill press receptacles
1-36 amp 208 volt 3 phase hot press
250- general purpose receptacles
1) minimum size overcurrent for feeder to lighting panel?
700, 600, 1000, 800
2) minimum rating in amps for air compressor disconnect?
378, 347, 242, 302
3) Excluding exemptions using THWN-2 copper wire which of the following meets minimum code requiremnets for a feeder supplying the lighting panel? (base answer on 1 conductor per phase in parallel conduits)
3 parallel 300 kcmill
3 parallel 500 kcmill
3 parallel 750 kc mill
3 parallel 800 kcmill
4) Minimum size transformer necessary to supply 208/120 volt loads
150 kva, 225 kva, 300 kva, 500 kva
5) Minimum bonding jumper in THWN? Phase conductors are 3 parallel THWN copper per phase in separate conduits
4/0, 3/0, 250 kcmill, 2/0
6) Minimum code requirement for the primary feed to transformer? THWN conductors, phase conductors are 2 parallel THWN copper per phase in single conduit.
2- 4/0, 2- 3/0, 2- 700 kcmill, 2-1000 kcmill
this is as far as i can get:
535 kw. 535x1000=535,000 va
535\831.36=643.52 amps
643.52x1.25=804 so 1000 amp?
or.. 643.52 amp= 700 amp overcurrent to lighting panel 125% for continuous lighting?
Any help would be great
Sent from my iPhone using Tapatalk
a) 480/277 lighting panel supplying 535 KW florescent lights
b) 2-250 hp 480 volt 3 phase air compressors
c) 480/208y/120 3 phase transformer which supplies
5- 10 hp 208 3 phase pump motors
3- 25 hp 208 3 phase vacuum pump motors
17- 20 amp 120 volt punch press receptacles
8-30 amp 120 volt volt drill press receptacles
1-36 amp 208 volt 3 phase hot press
250- general purpose receptacles
1) minimum size overcurrent for feeder to lighting panel?
700, 600, 1000, 800
2) minimum rating in amps for air compressor disconnect?
378, 347, 242, 302
3) Excluding exemptions using THWN-2 copper wire which of the following meets minimum code requiremnets for a feeder supplying the lighting panel? (base answer on 1 conductor per phase in parallel conduits)
3 parallel 300 kcmill
3 parallel 500 kcmill
3 parallel 750 kc mill
3 parallel 800 kcmill
4) Minimum size transformer necessary to supply 208/120 volt loads
150 kva, 225 kva, 300 kva, 500 kva
5) Minimum bonding jumper in THWN? Phase conductors are 3 parallel THWN copper per phase in separate conduits
4/0, 3/0, 250 kcmill, 2/0
6) Minimum code requirement for the primary feed to transformer? THWN conductors, phase conductors are 2 parallel THWN copper per phase in single conduit.
2- 4/0, 2- 3/0, 2- 700 kcmill, 2-1000 kcmill
this is as far as i can get:
535 kw. 535x1000=535,000 va
535\831.36=643.52 amps
643.52x1.25=804 so 1000 amp?
or.. 643.52 amp= 700 amp overcurrent to lighting panel 125% for continuous lighting?
Any help would be great
Sent from my iPhone using Tapatalk