Can a circuit breaker inside a bucket in a sq. d module 5 mcc be replaced with a new cb. Replacing a 15a with a 60a cb for new installation. Atleast 30 percent of the buckets are out of service since the equipment was removed from operation. All work in mcc will be done deenergized .
Is there another way for this to be done ? Or is this acceptable ?
Is there another way for this to be done ? Or is this acceptable ?