Is a OCPD or disconnecting means required on the load side of a transfer switch?
I've always included a main breaker in the panel on the load side of a transfer switch. On this particular project, the contractor wants to take out the main breakers in the panels (part of VE). I can't find if there is a requirement for a breaker on the load side of the ATS anywhere. Is this just a habit I've picked up along the way or is it an NEC requirement?
Thanks!
I've always included a main breaker in the panel on the load side of a transfer switch. On this particular project, the contractor wants to take out the main breakers in the panels (part of VE). I can't find if there is a requirement for a breaker on the load side of the ATS anywhere. Is this just a habit I've picked up along the way or is it an NEC requirement?
Thanks!