I will probably be adding question as I read through the manual.
Seems it say I need to make sure all loads are off before starting equipment. For you guys that have done a lot of these. What the best way to achieve this. A disconnect is all he really needs but he may leave on. What’s a good automatic solution. Was thinking to feed a timmer relay off each load to give phase converter time to run. The manual does not designate a time. Is 60 seconds long enough
Seems it say I need to make sure all loads are off before starting equipment. For you guys that have done a lot of these. What the best way to achieve this. A disconnect is all he really needs but he may leave on. What’s a good automatic solution. Was thinking to feed a timmer relay off each load to give phase converter time to run. The manual does not designate a time. Is 60 seconds long enough