Stevenfyeager
Senior Member
- Location
- United States, Indiana
- Occupation
- electrical contractor
I don't do commercial very often, can you please help me? A ground testwell is required on this job. What is that ? Also, 'contractor will perform a smoke test on all conduits installed.' What is a smoke test ? What is a "Pre and Post test" on all low voltage cables ? 'Provide one # 500 kcmil ground from service ground bar to (3) 10' ground rods.' 500 kcmil ? the blueprint didn't say Al or Cu. But either way, that size ? Why ?
The job is relocating a single phase 100 amp subpanel in a museum. GC just sent me the prints, I look at the job next week.
thank you so much!
The job is relocating a single phase 100 amp subpanel in a museum. GC just sent me the prints, I look at the job next week.
thank you so much!