It sounds like your comparing "Connected Load" with "Demand Load".vanetten said:Should the design be based on maximum loads and not predicted operating loads?
I never let clients tell me how to do my Electrical design. If your client insists on this type of design and you're not comfortable with it, ask for it in writing. That way, when breakers start to have nuisance trips 12 weeks down the road, you'll have paperwork to back up your design.vanetten said:The client is giving me a operating load, max. The equipment has max or full load specifications. They are telling us to size feeders and ocpd's according to the max operating load. What do you design to?
rr said:I never let clients tell me how to do my Electrical design. If your client insists on this type of design and you're not comfortable with it, ask for it in writing. That way, when breakers start to have nuisance trips 12 weeks down the road, you'll have paperwork to back up your design.