In Northern Va, there is one jurisdiction that is requiring CEEs to be Megged out in their presence if there was not an inspection. They dont accept certification. But the code (2006 IRC) says the 25 Ohms or less rule only applies to rod, pipe and plate electrodes. Most of their inspecters wont "schedule" inspections, just give you a window and it is difficult to get a builder to wait a day to pour footers.
Wondering if anyone else has similar issues and what they are doing about it