Hi,
Does anyone have a detailed spread sheet for taking off concrete pole bases. I am working on building an assembly in my estimating system however was hoping to see what other professionals are using.
Thanks,
Do you think you will be able to cover all the variables as no two pole bases are alike for different jobs, each can have many different requirements as well as cost, they can be flush with the ground raised above the ground, square, stone/brick faced, then there is the size and amount of concrete each will take as well as the re-bar cage?
Are you trying to say it is not possible to properly do an estimate for a project that would include a pole base?