Looking for some solutions. During a rushed conduit install I took an incorrect reference point measurement for the slab encased conduit. Only after the pour did I realize I was 18" away from my correct location (see picture).
The conduit was placed just below rebar in a 5" slab. First solution is to cut in a new trench just above rebar, but I'm trying to avoid that by tapping into the stub and cutting the 18" where I need to be.
Problem with that is I don't have much room to work with since the 90 deg elbow starts just an inch or two below the slab surface (see cross section photo)
Any chance I could flush mount a slab box and continue the run over to where I need it? It wouldn't be a junction since no splices would be used, but not sure if the inspector would raise an eye to that though.
Any thoughts?
The conduit was placed just below rebar in a 5" slab. First solution is to cut in a new trench just above rebar, but I'm trying to avoid that by tapping into the stub and cutting the 18" where I need to be.
Problem with that is I don't have much room to work with since the 90 deg elbow starts just an inch or two below the slab surface (see cross section photo)
Any chance I could flush mount a slab box and continue the run over to where I need it? It wouldn't be a junction since no splices would be used, but not sure if the inspector would raise an eye to that though.
Any thoughts?

