chevyx92
Senior Member
- Location
- VA BCH, VA
Situation: Three parallel runs of 3/4" EMT 100FT in length with about 270 degrees of bending involved in a drop ceiling working on 12 FT ladder securing conduit with caddy beat on straps. How many man hours should I figure? Is there a rule of thumb when figuring installing EMT? I dont have an estimating program or book yet. Thanks.