- Location
- Bremerton, Washington
- Occupation
- Master Electrician
A contractor was cutting off 4" PVC stubbed out and cut into the adjacent buried 4" PVC with 600 MCM feeders, about 4 months later it blew out, and $15,000 to cut, pull new, set j-box as emergency repair.
What are the NEC violations that occured when the wire was nicked?
This is one:
310.2 Conductors.
(A) Insulated. Conductors shall be insulated.
Thanks I have to have our rebuttal in tuesday and I am running out of ttime. They don't deny cutting the conduit...but say it should not of blown up (480V three phase)
What are the NEC violations that occured when the wire was nicked?
This is one:
310.2 Conductors.
(A) Insulated. Conductors shall be insulated.
Thanks I have to have our rebuttal in tuesday and I am running out of ttime. They don't deny cutting the conduit...but say it should not of blown up (480V three phase)