I just heard back from Eaton on the transformer. They said I can switch thistop the grounded 480/277 wye secondary for the same price, which puts me back to the grounding to meet a CSA/UL Listing (which is past my knowledge level)
the transformer will be sitting offline of our machine (right next to it due to weight)
there will be a connector on the cable going to the transformer on the Line Side(3 hot + ground)
there will be a connector on the cable going to the transformer on the Load Side(3 hot + ground)
There should now be a ground lug on the transformer chassis since we're switching to a WYE secondary. Do we just land the ground wires coming from both cables/connectors (the Line Side and the Load side) onto the ground lug and its good?