I have one tenant A1 space that is going to be divided into two tenant spaces A, B by demising wall.
At the moment scope of work only is to build demising wall only. However the new space created tenant space B is unoccupied i.e no tenant. Tenant space A has panelboard which has all of tenant space B branch circuits overcurrent protection devices.
I am confused by NEC 2014 section 240.24(B) which says each occupant needs ready access to its overcurrent protection devices because all of tenant space B branch circuits overcurrent protection devices are in tenant space A however tenant space B is vacant but has landlord at its owner.
Under the above situation would 240.24(B) apply so that we would need to add in scope of work branch circuits overcurrent protection devices in new panelboard in tenant B space or 240.24(B) would not apply?
At the moment scope of work only is to build demising wall only. However the new space created tenant space B is unoccupied i.e no tenant. Tenant space A has panelboard which has all of tenant space B branch circuits overcurrent protection devices.
I am confused by NEC 2014 section 240.24(B) which says each occupant needs ready access to its overcurrent protection devices because all of tenant space B branch circuits overcurrent protection devices are in tenant space A however tenant space B is vacant but has landlord at its owner.
Under the above situation would 240.24(B) apply so that we would need to add in scope of work branch circuits overcurrent protection devices in new panelboard in tenant B space or 240.24(B) would not apply?