ddcrawford
Member
I have constructed a new detached garage/workshop and want to find out if I am going down the right path to get power to it.
I am planning on a 100A two-pole breaker in my main house panel, running three #3 THHN and one #8 THHN ground to a GE TM1210 panel (100A main breaker, 12 space panel) and will install a ground rod at the garage.
Is this what I need to do (install a load center with a main breaker) to get around the 6 breaker rule? By doing this can I now use the full complement of breakers this box will handle if needed?
Is my approach a sound way of getting the power to the garage?
Thanks for the help!
I am planning on a 100A two-pole breaker in my main house panel, running three #3 THHN and one #8 THHN ground to a GE TM1210 panel (100A main breaker, 12 space panel) and will install a ground rod at the garage.
Is this what I need to do (install a load center with a main breaker) to get around the 6 breaker rule? By doing this can I now use the full complement of breakers this box will handle if needed?
Is my approach a sound way of getting the power to the garage?
Thanks for the help!