Article 220.87 allows for existing loads to be determined with maximum demand data if available for a 1-year period.
I have contacted the utility company for the peak demand load for 12 months. The plan check department in Las Vegas will not accept utility data because it is not stated in the code that way.
My question is: How do I gain that information if not through the utility.
I do not have time to hook-up a data recorder for a 30-day period as an alternative.
Thanks,
Dan Craven
I have contacted the utility company for the peak demand load for 12 months. The plan check department in Las Vegas will not accept utility data because it is not stated in the code that way.
My question is: How do I gain that information if not through the utility.
I do not have time to hook-up a data recorder for a 30-day period as an alternative.
Thanks,
Dan Craven