volt102
Senior Member
- Location
- New Hampshire
A stand alone dialysis center was designed to provide all emergency lighting by means of battery backup unit equipment. The dialysis equipment is provided with battery backup as well. If a 150 kva generator is provided with a whole building transfer switch that supplies backup power for all loads in the building, is this a code compliant design or will the optional loads require a separate transfer switch as well as all wiring be separated?